Dated Old Photographs
Topics:
|
Admiralty National Monument and Angoon Hydroelectric Project
U.S. Forest Service
SUMMARY: Pursuant to section 102(2)(C) of the National Environmental
Policy Act of 1969, the USDA Forest Service, Tongass National Forest,
will prepare an environmental impact statement (EIS) to address the
environmental effects and necessary mitigation measures for the
construction, maintenance, and operation of the Angoon Hydroelectric
Project on Admiralty Island, in Southeast Alaska.
The City of Angoon is the only permanent community on Admiralty
Island; it is approximately 60 air miles southwest of Juneau, Alaska.
The project are includes the lower 8,500 feet of Thayer Creek and the
area between Thayer Creek and the City of Angoon, located approximately
6 miles to the south. In addition, the project area includes an
underwater crossing of Kootznoowoo Inlet for a transmission line. All
project facilities, except for the underwater transmission line
crossing Kootznoowoo Inlet and the terminus in Angoon, would be located
on National Forest System lands. The project area includes portions of
Cooper River Meridian. T.49S, R67E, and T.50S, R67E.
DATES: Comments will be accepted throughout the EIS process; to be most
useful during the analysis, however, comments should be received in
writing on or before December 3, 2004. The draft environmental impact
statement is expected in May 2005, and the final environmental impact
statement is expected in August 2005.
ADDRESSES: Send written comments to Susan Marthaller, District Ranger,
Admiralty National Monument, 8461 Old Dairy Road, Juneau, Alaska, 99801
or email to smarthaller@fs.fed.us.
FOR FURTHER INFORMATION CONTACT: Susan Marthaller, District Ranger,
Admiralty National Monument, 8461 Old Dairy Road, Juneau, Alaska,
99801; phone 907-790-7472; fax 907-586-8795 or email to
smarthaller@fs.fed.us.
SUPPLEMENTARY INFORMATION: The City of Angoon has some of the highest
electric rates in Alaska. The Alaska National Interest Lands
Conservation Act of 1980 (ANILCA) section 506(a)(3)(B) granted
Kootznoowoo, Inc., the village corporation of Angoon, ``the right to
develop hydroelectric resources on Admiralty Island within township 49
south, range 67 east, and township 50 south, range 67 east, Cooper
River Base and Meridian, subject to such conditions as the Secretary of
Agriculture shall prescribe for the protection of water, fishery,
wildlife, recreational, and scenic values of Admiralty Island.'' ANILCA
also recognized the economic and cultural needs and expectations
associated with Kootznoowoo, Inc., (ANILCA Sec. 506(a)(3)(B).
Consultants for Kootznoowoo, Inc. completed the Angoon
Hydroelectric Project Feasibility Evaluation Report in march 2000 (HDR
Alaska 2000). The proposed operations are subject to approval of a Plan
of Operations under 36 CFR, part 228, which is intended to ensure that
adverse environmental effects on National Forest System lands and
resources are minimized.
Purpose and Need for Action
The purpose and need for the Angoon Hydroelectric Project EIS is to
determine how to develop the project while protecting the resources of
Admiralty Island National Monument. ANILCA granted Kootznoowoo, INC the
right to develop the hydroelectric project subject to mitigations
prescribed by the Forest Service for protection of water, fishery,
wildlife, recreational and scenic values of Admiralty Island.
Kootznoowoo, Inc., sent a letter to the Regional Forester on
November 19, 2003, requesting that the Forest Service begin the NEPA
work for the Angoon Hydroelectric Project. More recently, on April 21,
2004, Kootznoowoo, Inc., submitted an application asking for Forest
Service authorization for the project.
Kootznoowoo, Inc., the City of Angoon, and the Angoon Community
Association are pursuing funding to develop this hydroelectric project
with the expectation that it would reduce the cost of power generation
in Angoon and result in lower electric rates for Angoon residents. The
project is expected to benefit the local economy by creating
construction jobs and providing sufficient power for future growth of
the community.
Proposed Action
The Forest Service Proposed Action is to authorize, through special
use permits and easements, the construction and operation of a run-of-
river hydroelectric facility on Thayer Creek. ``Run-of-river'' refers
to operations in which the hydroelectric power facility uses only the
water that is available in the natural flow of the river. Under normal
conditions, run-of-river facilities involve little or not water
storage, and power generation fluctuates with the stream flow. Major
improvements associated with the 1,000-kilowatt hydroelectric power
facility include the following:
1. Port facilities located 1.8 miles south of the outlet of Thayer
Creek consisting of mooring buoys and a garage for operation and
maintenance vehicles.
2. A diversion dam, approximately 10 feet high, on Thayer Creek,
about 1.6 miles up from the outlet.
3. An intake structure at the diversion dam.
4. A pipeline, approximately 1.2 miles long, from the intake
structure to the powerhouse.
5. A penstock, about 510 feet long, from the pipeline to the
powerhouse.
6. A surge tank near the junction of the pipeline and penstock.
7. A power plant structure, about 30 feet by 68 feet and 25 feet
high, to house two generating units.
8. Three access roads including a 1.9-mile road from the port
facilities to the power plant, a 1.4-mile road from near the powerhouse
to the diversion dam/
[[Page 60977]]
intake structure, and an estimated 4.2-mile road from the port
facilities to Kootznoowoo Inlet.
9. A transmission line consisting of two overhead segments, 1.9
miles and 4.2 miles, and one submarine crossing, approximately 0.9
mile. The three segments would extend from the powerhouse to the port
facilities, from the port facilities to Kootznoowoo Inlet, and last,
from the northern shore of Kootznoowoo Inlet to the City of Angoon, on
the opposite shore.
In addition, various temporary facilities, including a barge
landing, staging areas, and a construction camp, would be needed during
project construction. The Feasibility Evaluation Report describes
existing Angoon electrical loads and resources and includes the
development schedule and an economic analysis.
The facilities, roads, and transmission lines would be designed to
meet Forest Plan standards and guidelines with an emphasis on:
1. Scenic visibility standards
2. Minimium impact to beach fringe and wetlands
A plan, subject to approval by the Forest Service and agencies with
permitting jurisdiction, would be required before implementation to set
performance criteria for achieving objectives related to beach fringe
and estuary, scenery, and heritage resources.
Possible Alternatives
In addition to the Proposed Action and No Action, alternatives
currently under consideration for analysis in the EIS include:
subterranean/submarine transmission line between Thayer Creek and
Angoon.
Responsible Official
Forrest Cole, Forest Supervisor, Tongass National Forest, 648
Mission Street, Federal Building, Ketchikan, AK 99901-6591.
Nature of Decision To Be Made
The decision to be made by the Forest Supervisor of the Tongass
National Forest is under what terms and conditions to authorize,
through special use permits and easements, the construction and
operation of a hydroelectric facility on Thayer Creek as described
above. The Forest Supervisor will also decide what mitigations, if any,
would be necessary to implement the action.
Scoping Process
Public scoping meetings are planned in Angoon at the Community
Services Building from 6 p.m. until 9 p.m. on Thursday, October 14,
2004, and in Juneau at Centennial Hall from 7 p.m. until 9 p.m. on
Friday, October 15, 2004.
Preliminary Issues
Potentially significant issues identified to date include potential
effects on the following: (1) Consistency with wilderness management
objectives, (2) visual resources.
Permits or Licenses Required
In an order issued January 23, 2001, the Federal Energy Regulatory
Commission (FERC) found that a license would not be required for this
project. FERC concluded that the Commission lacks jurisdiction to issue
a license for the proposed project due to its location in a National
Monument within the National Forest System. Because of this, the Forest
Service is the lead agency for this project, and a Forest Service
special use permit would be the primary agency authorization for the
project. Permits from other federal and state agencies would also be
required for specific portions of the project. Additional permits or
licenses may include the following:
1. U.S. Army Corps of Engineers
--Approval of discharge of dredged or fill material into the waters of
the United States under Section 404 of the Clean Water Act;
--Approval of the construction of structures or work in navigable
waters of the United States under Section 10 of the Rivers and Harbors
Act of 1899;
2. Environmental Protection Agency
--National Pollutant Discharge Elimination System (402) Permit;
--Review Spill Prevention Control and Countermeasure Plan;
3. State of Alaska, Department of Natural Resources
--Tideland Permit and Lease or Easement;
4. State of Alaska, Department of Environmental Conservation
--Solid Waste Disposal Permit;
--Certification of Compliance with Alaska Water Quality Standards (401
Certification)
Comment Requested
This notice of intent initiates the scoping process, which guides
the development of the environmental impact statement.
Early Notice of Importance of Public Participation in Subsequent
Environmental Review
A draft environmental impact statement (Management Bulletin number
R10-MB-528) will be prepared for comment. The comment period on the
draft environmental impact statement will be 45 days from the date the
Environmental Protection Agency publishes the notice of availability in
the Federal Register.
The Forest Service believes, at this early stage, it is important
to give reviewers notice of several court rulings related to public
participation in the environmental review process. First, reviewers of
draft environmental impact statements must structure their
participation in the environmental review of the proposal so that it is
meaningful and alerts an agency to the reviewer's position and
contentions. Vermont Yankee Nuclear Power Corp. v. NRDC, 435 U.S. 519,
553 (1978). Also, environmental objections that could be raised at the
draft environmental impact statement stage but that are not raised
until after completion of the final environmental impact statement may
be waived or dismissed by the courts. City of Angoon v. Hodel, 803 F.2d
1016, 1022 (9th Cir. 1986) and Wisconsin Heritages, Inc. v. Harris, 490
F. Supp. 1334, 1338 (E.D. Wis. 1980). Because of these court rulings,
it is very important that those interested in this proposed action
participate by the close of the 45-day comment period so that
substantive comments and objections are made available to the Forest
Service at a time when it can meaningfully consider them and respond to
them in the final environmental impact statement.
To assist the Forest Service in identifying and considering issues
and concerns on the proposed action, comments on the draft
environmental impact statement should be as specific as possible. It is
also helpful if comments refer to specific pages or chapters of the
draft statement. Comments may also address the adequacy of the draft
environmental impact statement or the merits of the alternatives
formulated and discussed in the statement.
Reviewers may wish to refer to the Council on Environmental Quality
Regulations for implementing the procedural provisions of the National
Environmental Policy Act at 40 CFR 1503.3 in addressing these points.
Comments received, including the names and addresses of those who
comment, will be considered part of the public record on this proposal
and will be available for public inspection.
(Authority: 40 CFR 1501.7 and 1508.22; Forest Service Handbook
1909.15, Section 21)
[[Page 60978]]
Dated: October 4, 2004.
Forest Cole,
Forest Supervisor.
|